Westminster Grove Construction update - August 2, 2010


- Kitchens/Living rooms are done and ready
- All appliances have been installed and furniture has been delivered
All bedroom furnishings have been delivered
We're almost ready for MOVE-IN WEEKEND!!
JUNE 21, 2010
Exterior Site Work:
- Curb and guttering and light bases for parking lot poured and soon ready for asphalt paving.
- Sidewalk north of building Oak installed.
- Modular block retaining wall on south end of building Cedar installed.
 |
Buildings: Oak and Maple - Exterior front porch columns installed.
- Dishwashers installed and stoves arriving on site.
|
| |
|
 |
 |
| |
|
| |
|
|
|
Building: Cedar - Interior cabinets installed.
- Primer coat on all interior walls completed.
- Exterior fully prepared for brick work to begin.
|
 |
| |
|
 |
 |
Westminster Grove Construction Update - May 18, 2010
Westminster Grove Construction Update - May 18, 2010
Building: OAK
- Interior doors and hardware installed
- Furnaces and water heaters set.
- Plank flooring installed in common areas.
- Kitchen cabinets installed.
- Light fixtures installed.
- Ceramic tile in bathrooms completed
------------------------------------------------------------------------
Building: MAPLE (on the left below)
- Drywall mudd/taping complete and sanding nearing completion
- Interior paint underway
- Exterior brick work nearing completion
------------------------------------------------------------------------
Building: CEDAR (see below)
- First floor framing competed.
- Interior mechanical/electrical/plumbing rough-ins started
- Exterior ready for roof shingles
----------------------------------------------------------------------
March/April 2010:
Brick laying in progress on OAK:
----------------------------------------------------------------------
IT wiring & utilities in progress on OAK:


----------------------------------------------------------------------
Graffiti Party before the walls are drywalled in OAK & MAPLE!!








----------------------------------------------------------------------
Exterior Prep for Brick on MAPLE (below):

----------------------------------------------------------------------
Interior Framing on MAPLE (below):


----------------------------------------------------------------------
Basement prep & pouring for CEDAR (below):

----------------------------------------------------------------------
OAK now looks like a real building!!

----------------------------------------------------------------------
Interior framing is done and is now waiting for Drywall in OAK:

----------------------------------------------------------------------
Framing up MAPLE's first floor:

----------------------------------------------------------------------
Original Westminster Grove Rendering - Front View of each building:

----------------------------------------------------------------------
Original Westminster Grove Rendering - Rear View of each building: