Construction Photo Gallery
December 5, 2007
Foundation walls continue
Underground plumbing rough-ins starting this week.
November 26, 2007
Foundation walls continue.
October 31, 2007
Footing excavation scheduled to begin this week.
October 24, 2007
Unsuitable soil removed and new sub-grade soil installed and rolled; ready for gravel.
Foundation excavation planned for next week.